2025

15 to 16 JanuaryCompleted

Kick-off meeting

Norway · hosted by FURIM Institutt

All six partners set project goals, agreed research methodologies and aligned on how data collection would run across the countries.

January to FebruaryCompleted

Research and data compilation

All partners

Surveys, focus groups and interviews with youth workers, gathering first-hand insight into what they knew and needed around immersive technologies.

March to MayCompleted

Local engagement and multiplier events

Led by CKM Dubrovnik, Croatia

Ten local events across the partner countries, bringing youth workers, educators and youth organisations into the research.

May to AugustCompleted

Data analysis and needs assessment report

Led by METU, Türkiye

The comprehensive needs assessment report, and with it the blueprint that decided which modules the curriculum would contain.

29 to 30 JuneCompleted

Transnational project meeting

Spain · hosted by SOMOS Europa

Review of the needs assessment and preparation for curriculum and platform development.

July to OctoberCompleted

Curriculum development

Led by METU, all partners contributing

Each partner drafted the module closest to its expertise. Overlapping topics were merged, taking the planned eight modules down to six.

November 2025 to March 2026Completed

3D platform development

Led by BEYOND42, Serbia

Design, environment build, navigation mapping and content upload for the virtual learning and development environment.

1 to 2 DecemberCompleted

Transnational project meeting

Poland · hosted by YES

Platform development strategy and alignment for the next project phase.

2026

12 JanuaryCompleted

Warsaw transnational meeting

CIC Warsaw, Poland · hosted by YES

The meeting that locked the platform down: the Info Desk user journey, the four areas, the eight-button module structure, registration and GDPR requirements, and the critical path for curriculum content.

28 January to 3 FebruaryCompleted

Curriculum content freeze and review

All partners, review by METU

Final module content submitted, METU feedback delivered on all six modules, partner revisions completed, and video production started.

26 to 27 MarchCompleted

Dubrovnik Expo panel

Croatia · hosted by CKM Dubrovnik

A panel discussion on MEFER at an event of around 65 attendees, including representatives of the European Parliament and the European Commission.

8 to 12 JuneCompleted

International implementation workshop

Øvre Norelia, Norway · hosted by FURIM Institutt

Five days with five people from each partner, one coordinator and four youth workers or educators. A full platform walkthrough and a module-by-module workshop, each presented by the partner who wrote it.

11 JuneCompleted

Final consortium meeting

Øvre Norelia, Norway

Partners agreed that the final six months are for completing, translating, designing and disseminating what already exists, rather than building anything new.

June to OctoberRunning now

Pilot phase on the platform

All partners

The platform opens to around 150 pilot users. Their feedback feeds the final round of content and interface fixes.

Through 2026Running now

Local implementation and dissemination

Led by CKM Dubrovnik

Each partner runs two local events of around 30 participants, plus newsletters, podcasts, media articles and conference presentations, tracked on a shared KPI dashboard.

15 SeptemberAhead

Final translations

Curriculum materials translated into the partner languages.

15 OctoberAhead

Design and layout

All materials laid out in the MEFER visual identity.

15 NovemberAhead

Final content integration

Everything uploaded into the platform in its final form.

1 to 15 DecemberAhead

Partner inputs and dissemination evidence

Partner reports and local event evidence delivered to the coordinator for consolidation.

31 DecemberAhead

Final report and project close

The final report goes to the National Agency and the funded period ends. The platform stays online.